====== Scheduling ======
===== Manually Scheduling Tasks =====
You can manually assign and schedule tasks. Even if you are using auto scheduling you can still use the ''%%Task Maintenance%%'' screen to make changes or add additional tasks.
You can access the //Task Maintenance%// screen directly from the Sales Screen
* Click on the ''Tasks'' button at the top:
\\
{{ :production:scheduling:selection_025.jpg?direct |}}
\\
You can also access the ''%%Task Maintenance%%'' screen from the //Job Board//
* Click on the ''%%Tasks%%'' tab, then ''Edit Tasks'':
\\
{{ :production:scheduling:selection_026.jpg?direct |}}
\\
The Re-schedule button will automatically update all the dates of the tasks based on how you setup the dates for each affected department in the [[setup:system#departments|Department Maintenance]] screen.
\\
{{ :production:scheduling:selection_027.jpg?direct |}}
----