Table of Contents

Scheduling

Auto Scheduling

FastManager's auto scheduling module will do the following the first time you create a WIP:

  1. Scan you work order detail
  2. Select the correct machines
  3. Calculate the production time
  4. Scan your current production to available time
  5. … and then assign and schedule all the required tasks to the appropriate departments
When FastManager scans your order it looks at the embellishment price list you selected and makes choices based on those price lists.
If you think about it, You would not run at the same speed when printing fleece as you would when printing T-Shirts or if you are more familiar with embroidery, you would not run your machine at the same speed if you have metallic thread in the design.

In order for FastManager to make the accurate choices, you need to tell it how your business operates by doing the following:

Be conservative! Rather underestimate your production times that overestimate them.
You can always come back later and bump up the speed of certain departments.

Machine Setup

In order to use FastManager's auto scheduling module you would need to tell FastManager what production equipment you have.

From the Scheduling menu select a machine type. You will then list all the machines of that type that you have:



You will see a list of your current machines:

You cannot delete a machine if it is linked to one of your price lists.


Remember to click Save to commit your changes. You can also click on the Save and New button to immediately start adding another machine.


There will be different questions depending on the machine type.

Other options that will differ depending on the machine type:


Price List Parameters

FastManager makes scheduling choices based on the price list you select. This includes:



There are two aspects to creating any of these pricelists:
  1. Machine selection and time. (The actual embellishment), and
  2. Additional services which may or may not be charged for, but which need to be included in the schedule (ie: a Task needs to be created for the charge, or it may impact on the total machine time).

Machine selection

When editing your embellishment item, go to the Autoschedule Machines tab and click on Add to add a new machine to the list



FastManager will first compile a list of machines that can run your job, based on the price list you selected and other parameters such as order quantities, stitch counts and print colors.

*For example:*
If you are embroidering a quantity of 8 very detailed tank tops, you would not want FastManager to select your 15 year old 12 head machine.
For screen printing companies you would not want to select your old manual press to do 500 black tees with a 6 color simulated process job.

Additional charges.

While editing your embellishment price item, go the Additional Charges tab and click on Add



Additional charges have a two-sided impact:

You may need to schedule an additional department to execute the task with different time parameters.
OR
The additional charge may simply increase your machine production time.

*For example:*
If the additional charge is Screen Making you would want to assign and schedule a task for your Screen Making department a day or so before you are planning to print the job.
If the additional charge is Printing on Fleece you may want to simply add an additional 5 seconds per garment to your print time to compensate for slower squeegee speeds.
All price lists behave in the same manner with regards to additional charges.

First you need to tell FastManager if the additional charge should be included when Auto Scheduling.

*For example:*
If the additional charge is 'Printing on Fleece' you would have the same quantity in that line item as the number of prints.
If you select to add 5 seconds then FastManager will multiply the 5 seconds with the line item quantity.
On the other hand if the additional charge is 'Screen Making' then FastManager will create a new task for the screen department and assign the time based on the number of seconds you specify multiplied by the line item quantity which should be the number of screens you are making.




Auto Sheduling Compatibility Wizard

If you delete an embellishment price list then FastManager will have nothing to refer to when trying to schedule, if by any chance you convert quotations still quoted with those prices to work orders.

If you delete existing embellishment prices lists it is recommended to run the compatibility wizard.

The compatibility wizard will go through all previous orders as well as existing quotations and see if there are any embellishment price lists in use that no longer exist. FastManager will then ask you to specify a new or substitute price list.




Tasks

What makes FastManager unique is that you can assign and schedule tasks to various departments.

FastManager can assign tasks to your screen making, ink mixing etc, to ensure that all those tasks are complete before you try to setup your machine.